The PIO of the GMC explained that the covers were not returned by him and he was not aware of it. On being asked whether there were arrangements for receiving applications from the public on the RTI Act in the GMC main office and in all the branches of GMC in the city he replied in the negative. It was obviously a case of failure on the part of the GMC to make appropriate arrangements for receiving the petitions from the public under the RTI Act.
The petitions relate to information regarding cleaning of drains within the Corporation limit and construction and repair of roads at Lachit Nagar by the GMC. The PIO of the GMC came prepared with the replies to the issues raised in the petitions and the same were handed over to the petitioner during the hearing. The petitioner was asked whether she was satisfied with the replies and she replied in the affirmative. The Commission however mentioned that she should go through the replies furnished by the PIO, GMC and if any further information / clarification are required she should immediately bring it to the notice of the PIO, GMC who will furnish additional information.
Decision of the CommissionThe Commission was unhappy to find that the GMC has not taken action to fulfill its obligation to the public as mandated under section 4 of the RTI Act. Even a simple notice board has not been put up in any of the GMC offices informing the public about the PIO or to whom they should submit their applications for information. It was also found that GMC collected unauthorizely a fee of Rs. 5/- from an applicant namely Ms. Alpana Devi Choudhury on 19 July 2006, who is present here, when she personally submitted an application under the RTI Act.
The Commission gives the following directions to the GMC for immediate
compliance:
1. to designate APIOs under section 5 (2) of the RTI Act 2005 in order to
facilitate submission of requests by the public in all branches of GMC,
2. to prominertly display the names of PI Os and APIOs in all the offices
of the GMC,
3. As the PIO and APIOs may not be available to receive the petitions from
the public all the time, to open RTI counters in all the offices of the
GMC to accept the petitions from public and to help them out in submitting
the petitions etc. as required under section 6 (1) ,
4. to transfer misdirected petitions to the appropriate authorities under
section 6 (3) of the RTI Act, 2005,
5. to refund Rs. 5/- collected unauthorisedly from the petitioner Ms. Alpana
Devi Choudhury, and
6. to sensitise the staff of GMC on issues relating to RTI Act / Rules.
These directions will be complied with within 7 days by the GMC.
The petitioner is at liberty to approach the Commission again if she is not
satisfied with the response/ action taken by the GMC as directed herein.
(R.S. Mooshahary)
Chief Information Commissioner, Assam
Janata Bhawan, Dispur.
Authenticated true copy
(A.C. Sarma)
Under Secretary
State Information Commission, Assam
Janata Bhawan, Dispur.
CC:
1. Shri Parag Mahanta, ACS, Collector, Public Information Officer GMC, Guwahati
2. Ms. Gayatri Bhuyan Lachit Nagar Main Road House No. 29, Ulubari
Guwahati -781007, Assam.
3. Office file