PROCEEDINGS OF THE ASSAM INFORMATION COMMISSION FULL COMMISSION

Case No.173/2007

Dated 05-07-2007

Name of the Complainant:
Sri Jitendra Nath Gogoi
ViII Pamohi P.O. Garchuck, Guwahati, Assam.

Name of the Public Authority/SPIO:
Principal C.C.F. Assam, Guwahati

The following were present:
1. Shri Purnananda Bordoloi, IFS
DCF (M&E) & PIO,O/O the P.C.C.F, Assam, Public Authority
2. Sri Jitendra Nath Gogoi,Complainant

The complainant present. Shri Purnananda Bordoloi, DCF (M&N) & SPIO of the office of the Principal Chief Conservator of Forest, Assam present. The Principal Chief Conservator of Forest, Assam showed cause for his absence which was accepted by the Commission.

Brief of the case
Shri Jitendra Nath Gogoi submitted a complaint -on 23.5.07 stating that he sought information relating to Moinakhurung Stone querry 'A' from the SPIO of the office of the - Chief Principal Conservator, Assam, Guwahati but he did not receive any information within the stipulated time of 30 days. The information sought for are as follows:

(1) The boundaries of MoinaKhurung stone quarry 'A' for which the Mahal was settled, name of the Mahaldar.

(2) Distances from PWD road, school, ASEB lines, residential houses- village,agricultural field to the said Mahal.

(3) Steps taken to control pollution due to blasting and steps to mitigate the sufferings.

Submission by the parties
The Complainant submitted that he did not receive the information sought for by him from the SPIO and hence he filed this complaint. The SPIO submitted that he received the application on 19.3.07 and on the same day, he sent it to the DFO West Division. He obtained the information from DFO West Division on 27.3.07 and he sent the information on 9.4.07 by post. He also showed the issue register. He stated that he has maintained a separate receipt - register for RTI applications which he showed to the Commission. He also showed the reply to the complainant and the complainant expressed his satisfaction.

Observation of the Commission
The Commission perused the records including the issue register and docket register for R TI applications and expressed its satisfaction for proper maintenance of records on R TI matters. The Commission was satisfied that the information was sent in time by post but the petitioner did not receive the same. .

Decision of the Commission
The Commission on a careful consideration of the facts and circumstances of the case decided to direct the SPIO to furnish a copy of the information to the petitioner on realization of the cost from the petitioner, within 3 days of the receipt of this order.

Sd/- (R.S. Mooshahary)
Chief Information Commissioner, Assam
Janata Bhawan, Dispur.


Sd/- (Dr. B K Gohain)
State Information Commissioner, Assam
Janata Bhawan, Dispur.


Authenticated true copy

(Jiauddin Ahmed)
Secretary, State Information Commission, Assam
Janata Bhawan, Dispur.

Memo No SIC. 192/2007/20 dated July 5, 2007

CC:
1. The Principal Chief Conservator of Forest, Assam, Guwahati
2. The SPIO of the office of Principal Chief Conservator of Forest, Assam, Guwahati
3. Shri Jitendra Nath Gogoi, VilI. Pamohi, P.O. Garchuck, Guwahati - 35.
4. The,DIPR, Dispur, Guwahati.
5. The DIPR, Dispur, Guwahati.
6. MD, AMTRON, Bamunimaidan
7. Office file.


Secretary
State Information Commission, Assam